Looking ahead to a busy quarter at Granada
With three large wind farm contracts in build, the offshore teams are really busy. Granada have already delivered nearly 60 davits from an order of 175 to the DONG Hornsea project, as well as 70 davits from the 84 ordered for the Beatrice Wind Farm, and delivery of fully hydraulic cranes will commence shortly for the Scottish Power East Anglia 1 Wind Farm.
Looking forward to the next quarter, Mark Sidwell, director at Granada, commented, “We are extremely pleased with the breadth and scope of contracts won and being successfully delivered across all areas of the company. That we have such a range of prestigious clients, with significant orders, is testament to the dedication and the expertise of all our staff – from our Rochdale headquarters to our Broughton base and our engineers on-site at wind farms throughout the UK.”