2024-12-26
https://w3.windfair.net/wind-energy/pr/44617-rystad-energy-offshore-wind-turbine-europe-manufacturing-capacity-tower-component

News Release from Rystad Energy

No_logo

Wind Industry Profile of


Shortage looming as Europe's demand for offshore wind towers to surpass manufacturing capacity by 2028

Offshore wind developments are a critical component of Europe’s energy transition plans, but a supply headache could be on the horizon for the industry before the end of the decade. Rystad Energy’s modeling shows that in 2028, demand for offshore turbine towers will outstrip manufacturing capacity, signaling that time is running out for the continent to address the issue and ramp up production capabilities.

Rystad Energy’s offshore wind capacity outlook shows that wind tower manufacturing capacity will keep pace and exceed demand before 2028. However, that year is the turning point, and in 2029, demand will surpass manufacturing capacity by a significant margin. Steel demand for offshore wind towers will total more than 1.7 million tonnes in 2029, but manufacturing capacity will be a maximum of around 1.3 million tonnes, meaning supply can only meet about 70% of demand.

If Europe is to reverse this trend, manufacturers need to initiate expansion in the next two years, since it takes between two and three years to build new facilities. These forecasts assume no major steel shortage, so manufacturers can work at full capacity. If a shortage materializes, Europe could face a supply issue even earlier than expected.

"Turbine sizes keep growing as the importance of offshore wind to the global power grid accelerates, and tower demand is projected to surge accordingly. This is a golden opportunity for manufacturers to capitalize on increased demand, but new capacity needs to be added imminently if Europe is going to avoid a supply headache" said Alexander Flotre, vice president, Rystad Energy.

Learn more with Rystad Energy’s Wind Solution. 

Since constructing a tower manufacturing facility can take three years, European producers must initiate more expansions within the next two years, at the latest. They should not find this problematic as wind towers are made of steel, with no particularly complex or specialized machinery required.

While the average turbine capacity fixed in Europe in 2023 is expected to reach almost 10 megawatts (MW), Rystad Energy estimates that 50% of the total turbines installed between 2029 and 2035 will be bigger than 14 MW, with some projects forecasting to build 20-MW at the beginning of 2030.

It is instructive to note that a tower’s weight varies with the hub height, which is required to be more than half of the rotor diameter – excluding the clearance to the water surface – and which fluctuates from country to country.

In addition, as rotor dimensions grow, turbine sizes increase and larger towers are required. This growth is more prominent in Europe, where offshore wind developers have requested turbines of 12 MW or larger for their projects.

Spain and Denmark lead European offshore wind tower supply, accounting for about 90% of the estimated 1.1 million tonnes of the continent’s supply.

For more analysis, insights and reports, clients and non-clients can apply for access to Rystad Energy’s Free Solutions and get a taste of our data and analytics universe. 

Source:
Rystad Energy
Author:
Press Office
Link:
www.rystadenergy.com/...
Keywords:
Rystad Energy, offshore, wind turbine, Europe, manufacturing, capacity, tower, component



All news from Rystad Energy

No_logo

news in archive


Thematically suitable Windfair.net members in the business directory

  • Newlist_reyher
  • Newlist_eno_energy_ogo_claim
  • Newlist_logo.hodijcoatings
  • Newlist_logo.deublin
  • Newlist_bmu_logo
  • Newlist_logo.argentinaeolica.org
  • Newlist_energiequelle_logo
  • Newlist_8.2_logo_original_twocoloured_screen
  • Newlist_ts_logo_rgb
  • Newlist_windrad_logo-1-rgb
  • Newlist_logo.engr.wisc
  • Newlist_wpd-logo
  • Newlist_weidmueller_logo
  • Newlist_cga_logo
  • Newlist_xervon_engl_logo
  • Newlist_logo.schraubenwerk
  • Newlist_schaeffler_logo
  • Newlist_logo.overspeed
  • Newlist_juwi_logo_mit_verlauf_digital_srgb
  • Newlist_logo.aero_dynamik_consult
  • Newlist_logo.tuev-sued-offshore

more results



Keyword Search

© smart dolphin Gmbh 1999 - 2024 | Legal Notice | Windfair Editors | Privacy Policy | The Windfair Pocket Wind 2020