2024-11-05
http://w3.windfair.net/wind-energy/news/38756-rwe-triton-knoll-uk-offshore-wind-farm-turbine-installation-commissioning-vestas-mw-completion-electricity-green-deme-wind-osprey

UK: all turbines installed at Triton Knoll

Triton Knoll consists of 90 turbines, each one up to 187 metres tall with blades of over 80 metres long.

Official Press Release RWE:

Triton Knoll installs its final turbine

Wind Industry Profile of
Triton Knoll installs its final turbine

Project remains on schedule to complete turbine commissioning in 2021 and final project completion in 2022 / Each of the 90 state-of-the-art turbines can power a typical home in the UK for 29 hours with just one rotation

Triton Knoll, the most powerful offshore wind farm being constructed by RWE, has installed its final turbine, marking a significant stage in the project’s construction. The last of the state-of-the-art Vestas 9.5 megawatts (MW) turbines was erected earlier today, ensuring the project remains on track to complete turbine commissioning in 2021 and achieve final project completion in 2022. Triton Knoll is jointly owned by RWE (59%), J-Power (25%) and Kansai Electric Power (16%), with RWE leading both the wind farm’s construction and the... ... More: Official Press Release RWE

Keywords:
RWE, Triton Knoll, UK, offshore, wind farm, turbine, installation, commissioning, Vestas, MW, completion, electricity, green, DEME, Wind Osprey







Thematically suitable Windfair.net members in the business directory

  • Newlist_kaeufer_logo
  • Newlist_logo.windfair-us
  • Newlist_logo.drakawind

more results



Keyword Search

© smart dolphin Gmbh 1999 - 2024 | Legal Notice | Windfair Editors | Privacy Policy | The Windfair Pocket Wind 2020