04/16/2005
Turbulence hits Britain's wind power plans
Plans to build dozens of wind farms off the United Kingdom coast face delays that threaten to derail the government’s goal for a big increase in renewable energy. Offshore wind farms have come up against a series of obstacles — from the discovery of flocks of seabirds at sites in the Irish Sea, to uncertainty about funding costs of new grid connections and difficulties getting finance. “It will be very difficult for the government to keep to its target for offshore wind,” Mark Woodall of finance house Climate Change Capital told a renewable energy seminar. “With the current economics, offshore wind will not reach the 3-4 gigawatt capacity the government is relying on.”
The government is banking on offshore wind power to provide about 40 percent of its 2010 target of generating 10 percent of the UK’s power from green sources. The first two commercial projects are up and running off the coasts of Norfolk and north Wales, but others have been delayed. Offshore leases for 17 projects proposed in the first licensing round in 2001 are due to be completed by this July but not all sites will be ready, said the Crown Estate, which awards offshore licenses. “We are seeing steady progress but obviously not as fast as we had hoped,” Frank Parrish, head of marine estates at the Crown Estate, said. The British Wind Energy Association estimates that about 10 of the 17 wind farms will be built by the target date of 2007.
More ambitious farms with hundreds of turbines were proposed in round two for sites in the Irish Sea, off the Wash in eastern England and the Thames Estuary but these face delays if concerns over funding grid links are not sorted out soon. “The grid issue is causing consternation. If we want to make the 2010 deadline the grid work has to start now,” said Gordon Edge, head of offshore at the BWEA. Under its license, the National Grid has to seek guarantees from generators planning new power stations that they will cover the costs it incurs extending the grid if they decide not to go ahead with their plant. Expanding the grid could cost nearly $2 billion and offshore developers say they cannot take the risk and give these guarantees, as they do not have all the consents in place so some projects might not go ahead.
Regulator Ofgem says it is in talks with National Grid and the Department of Trade and Industry about the problem. For financiers, the high risks involved in using new offshore technology raises funding costs although these will drop in future as the industry gains experience, said Shane Bush, head of renewable energy at Standard Chartered Bank. “Once these pilot projects (in Norfolk and north Wales) start to bed down and it becomes understood how much it costs to run them, then lender requirements will reduce,” Bush told a seminar on renewable energy.
The government is banking on offshore wind power to provide about 40 percent of its 2010 target of generating 10 percent of the UK’s power from green sources. The first two commercial projects are up and running off the coasts of Norfolk and north Wales, but others have been delayed. Offshore leases for 17 projects proposed in the first licensing round in 2001 are due to be completed by this July but not all sites will be ready, said the Crown Estate, which awards offshore licenses. “We are seeing steady progress but obviously not as fast as we had hoped,” Frank Parrish, head of marine estates at the Crown Estate, said. The British Wind Energy Association estimates that about 10 of the 17 wind farms will be built by the target date of 2007.
More ambitious farms with hundreds of turbines were proposed in round two for sites in the Irish Sea, off the Wash in eastern England and the Thames Estuary but these face delays if concerns over funding grid links are not sorted out soon. “The grid issue is causing consternation. If we want to make the 2010 deadline the grid work has to start now,” said Gordon Edge, head of offshore at the BWEA. Under its license, the National Grid has to seek guarantees from generators planning new power stations that they will cover the costs it incurs extending the grid if they decide not to go ahead with their plant. Expanding the grid could cost nearly $2 billion and offshore developers say they cannot take the risk and give these guarantees, as they do not have all the consents in place so some projects might not go ahead.
Regulator Ofgem says it is in talks with National Grid and the Department of Trade and Industry about the problem. For financiers, the high risks involved in using new offshore technology raises funding costs although these will drop in future as the industry gains experience, said Shane Bush, head of renewable energy at Standard Chartered Bank. “Once these pilot projects (in Norfolk and north Wales) start to bed down and it becomes understood how much it costs to run them, then lender requirements will reduce,” Bush told a seminar on renewable energy.
- Source:
- Online Editorial www.windfair.net
- Author:
- Trevor Sievert, Online Editorial Journalist
- Email:
- press@windfair.net
- Keywords:
- UK, Britain, wind energy, renewable energy, wind farm, wind turbine, windmill, rotor-blade, offshore, onshore