2024-11-24
http://w3.windfair.net/wind-energy/news/41951-jan-de-nul-france-offshore-wind-farm-installation-wind-turbine-schedule-transport-logistics-saint-nazaire

News Release from windfair.net

List_windfair_logo_pos

Wind Industry Profile of


Saint-Nazaire Offshore Wind Farm: Jan De Nul finishes turbine installation

Jan De Nul said, the installation of France's first commercial-scale offshore wind farm was finished significantly ahead of schedule.

Installation began on 1 April, while on 5 September, the 80th and last turbine was successfully installed. Meanwhile, Jan De Nul’s Offshore Jack-Up Installation Vessel Vole au vent transported and installed 80 sets of 6 MW wind turbines for the first commercial wind farm in French waters. This wind farm will have a total capacity of 480 MW, which is equivalent to 20% of the Loire-Atlantique’s annual electricity consumption.

Pieter Vandezande, Project Manager at Jan De Nul Group: “The Saint-Nazaire wind farm is a milestone project for Jan De Nul, as this is France’s first offshore wind farm. We are proud to support the country in its energy transition by making possible the delivery of the first electricity produced by the very first French offshore wind farm. The exceptional installation progress has been the result of an extensive engineering process, optimized vessel preparation and planning, and an excellent collaboration with Parc éolien en mer de Saint-Nazaire and the turbine supplier GE.”

 

Source:
Jan De Nul
Author:
Windfair Editors
Email:
press@windfair.net
Keywords:
Jan De Nul, France, offshore, wind farm, installation wind turbine, schedule, transport, logistics, Saint Nazaire



All news from windfair.net

List_windfair_logo_pos

news in archive


Thematically suitable Windfair.net members in the business directory

  • Newlist_logo.windfair-us

more results



Keyword Search

© smart dolphin Gmbh 1999 - 2024 | Legal Notice | Windfair Editors | Privacy Policy | The Windfair Pocket Wind 2020