Jan De Nul finishes Taiwan Power Company Offshore Windfarm Phase 1 Project
Official Press Release Jan De Nul:
Jan De Nul completes installation of all wind turbines at TPC Offshore Wind Farm
Jan De Nul Group completed the installation of all 21 offshore wind turbines for the 109.2 MW Taiwan Power Company Offshore Windfarm Phase 1 Project – Demonstration, including the installation of all subsea cables. The project teams of Jan De Nul and Hitachi now proceed with the termination and commissioning process of the complete offshore wind farm.
The project was kicked off in September 2018 with the preparatory onshore cable works. On 12 June 2021, Jan De Nul’s Offshore Jack-Up Installation Vessel Taillevent successfully completed the installation of the last 5.2 MW Hitachi wind turbine for Taiwan Power Company (TPC). Jan Kop, Project Director TPC Project for Jan De Nul Group: “With this major milestone we have now reached the final stretch of... ... More: Official Press Release Jan De Nul
- Keywords:
- Jan De Nul, Taiwan, installation, turbine, demonstration, subsea cables, site, offshore, vessel, downwind rotor, typhoon, jack-up vessel