2024-11-24
http://w3.windfair.net/wind-energy/news/37535-acciona-wind-turbine-energy-spain-wind-farm-onshore-pilot-project-biomass-ashes-operations-construction-nordex-manufacturer-towers

ACCIONA to start construction work on Spanish Celada Fusión wind farm

The wind farm will include 10 Nordex 149 wind turbines that will be installed atop 125-meter-high steel towers.

Official Press Release ACCIONA:

ACCIONA starts construction of Celada Fusión wind farm (48MW) in Spain

Wind Industry Profile of
ACCIONA starts construction of Celada Fusión wind farm (48MW) in Spain

First quarter 2022: The wind farm will require an investment of more than €45M and will start operations early next year / Circular economy: The facility will include a pilot project for the reuse of biomass ashes

ACCIONA has started construction works on the Celada Fusión wind farm (48MW) in the Valles del Cerrato region, in Palencia (Spain). The project will require an investment of more than €45M and will commence operations in the first quarter of 2022. The wind farm includes 10 Nordex 149 wind turbines that will be installed atop 125-meter-high steel towers. The turbines, among the most powerful units developed for onshore wind power, are the first of this series to be installed in Spain and were manufactured at the Nordex plant in Vall... ... More: Official Press Release ACCIONA

Keywords:
ACCIONA, wind turbine, energy, Spain, wind farm, onshore, pilot project, biomass ashes, operations, construction, Nordex, manufacturer, towers







Related News

Thematically suitable Windfair.net members in the business directory

  • Newlist_logo.drakawind
  • Newlist_logo.windfair-us
  • Newlist_kaeufer_logo

more results



Keyword Search

© smart dolphin Gmbh 1999 - 2024 | Legal Notice | Windfair Editors | Privacy Policy | The Windfair Pocket Wind 2020