Posted by: Windfair Editors
Analysis: Bottleneck for Heavy Lift Vessels Approaching
Official Press Release Rystad Energy:
The world may not have enough heavy lift vessels to service the offshore wind industry post 2025
Offshore wind is booming, and as turbine and project sizes grow, demand for specialized installation vessels will soar. The market for vessels capable of installing large offshore wind components is quickly being outpaced by growing demand from the global development pipeline, a Rystad Energy analysis shows. The global fleet will be insufficient to meet demand* after 2025, opening room for more specialized vessel orders and other oil and gas heavy lift vessel conversions.
When translating the volume of offshore wind projects into vessel years for installation scopes, we estimate that the demand for foundation and turbine installations in 2020 is approximately 8 and 13 years respectively. On the supply side of the equation, there are currently 32 active turbine installation... ... More: Official Press Release Rystad Energy
- Keywords:
- Rystad Energy, analysis, study, vessel, offshore, wind industry, demand, wind farm, work, construction, Asia, installation vessel, turbine, handling