TÜV SÜD Assesses Planned 372 MW Wind Project in Sweden
Official Press Release TÜV Süd:
TÜV SÜD assesses planned 372 MW wind energy project in Sweden for Prime Capital and Enlight
On behalf of Prime Capital AG and Enlight, TÜV SÜD reviews the technical aspects of a large, planned wind energy project in Sweden. With a total capacity of 372 MW, the Björnberget wind farm is one of the largest onshore wind energy projects in Europe that are scheduled to start construction this year. As a Technical Advisor (TA), TÜV SÜD makes a significant contribution to investment security.
Over the next two years, a wind farm with a total of 60 SG 5.X-170 wind turbines from Siemens Gamesa Renewable Energy will be built at the Björnberget site in central Sweden. The turbines have a nominal output of 6.2 megawatts and the largest rotor diameter in the onshore sector. The Björnberget project is being built and managed by Prime Capital AG. Construction is scheduled... ... More: Official Press Release TÜV Süd
- Keywords:
- TÜV Süd, Prime Capital AG, Enlight, Technical Advisor (TA), Björnberget, wind farm, capacity, wind turbine, investment security, Europe, Siemens Gamesa Renewable Energy