First Offshore Wind Power for Taiwan
Formosa 1 will be Taiwan’s soon-to-be first commercial-scale offshore wind farm, the second phase of Formosa 1 produced its first power. The second phase of Formosa 1 will comprise 20 Siemens Gamesa 6MW offshore wind turbines. 10 of these have now been installed, and six of them have started gradually generating power, as project developer Ørsted has announced..
Before commercial operation, each wind turbine needs to go through a power generation test lasting between 10 to 14 days to complete the commissioning stage. The 20 wind turbines for the second phase of Formosa 1 are expected to be fully operational within the next two months.
Matthias Bausenwein, Formosa 1 Chairman and President of Ørsted Asia-Pacific, says: “First power from the second phase of Formosa 1 is a major milestone for the project before completion. An achievement by the Formosa 1 team and all our supply chain partners. Together with our joint venture partners, JERA, Macquarie Capital and Swancor, we’ll keep devoting our efforts to building Taiwan’s first offshore wind farm on time and within budget. Formosa 1 is committed to producing significant amounts of clean energy and contribute to Taiwan’s energy transition.”
- Source:
- Ørsted
- Author:
- Windfair Staff
- Email:
- press@windfair.net
- Keywords:
- Ørsted, wind farm, Taiwan, offshore, renewable energy, production, second phase, Formosa 1, comissioning, Siemens Gamesa, turbine, installation