Posted by: Windfair Editors
First Trial Operation At Nordsee One Offshore Wind Farm Started
Official Press Release Nordsee One GmbH:
Nordsee One Achieves First Power
First wind turbine now in trial operation / 7 of 54 turbines have now been installed / Commercial commissioning of the 332 megawatt wind farm anticipated by the end of 2017
The first electricity from the Nordsee One offshore wind farm, located off the German coast, began flowing shoreward yesterday. The first turbine successfully generated power and is already feeding green electricity into the grid. “The generation of first power represents the achievement of an essential project milestone”, noted Tim Kittelhake, Managing Director (COO) of Nordsee One GmbH. “With this accomplishment behind us, we remain focused on the work ahead of us over the coming months.” Nordsee One reached financial close in March, 2015. All 54 foundation... ... More: Official Press Release Nordsee One GmbH
- Keywords:
- Nordsee One, offshore, wind farm, North Sea, Germany