2024-11-05
http://w3.windfair.net/wind-energy/news/22238-us-turbine-blades-arrive-in-rhode-island-crews-readying-for-busy-construction-season

News Release from windfair.net

List_windfair_logo_pos

Wind Industry Profile of


US: Turbine Blades Arrive in Rhode Island; Crews Readying for Busy Construction Season

Offshore construction activities are beginning to ramp up for the Block Island Wind Farm, with the arrival this week of the 240-foot long turbine blades at Deepwater Wind and GE’s assembly facility at ProvPort.

Yesterday morning, local stevedores began offloading the 15 blades at the Providence port facility. The blades, and the tower sections already assembled there, are scheduled to travel by boat to the Block Island Wind Farm site in the beginning of August.

GE is supplying the 6-megawatt Haliade 150 offshore wind turbines for the Block Island Wind Farm. The blades were built in Denmark by GE’s subcontractor, LM Wind Power.

Meanwhile, installation of the submarine cables for the wind farm and the Island’s new connection to the mainland are making significant progress: The 6.5-mile submarine cable connecting the wind farm to Block Island has been installed. In addition, National Grid’s 17-mile sea2shore cable connection between Block Island and mainland Rhode Island reached a major milestone last week with the successful landing of the cable on Block Island’s shore. In July, Deepwater Wind will complete the cable connections between the wind turbines themselves.

Source:
Deepwater Wind
Link:
dwwind.com/...



All news from windfair.net

List_windfair_logo_pos

news in archive





Keyword Search

© smart dolphin Gmbh 1999 - 2024 | Legal Notice | Windfair Editors | Privacy Policy | The Windfair Pocket Wind 2020