Senvion SE has just completed commissioning of phase one of the wind project Rivière-du-Moulin. So far, 75 of 175 Senvion MM82 and MM92 type turbines in a special cold climate version (CCV) have been installed and commissioned.

Completion of phase two, consisting of 100 additional turbines, is set for end of 2015. By now, Senvion has a footprint of almost 800 megawatts (MW) in Quebec that the company’s local team installed and commissioned since 2010.

The wind project, located in the Regional County Municipalities (RCM) of Charlevoix and Fjord du Saguenay, will be the largest wind energy facility in Canada signed under a single Power Purchase Agreement. With 350 MW it is also one of the two biggest onshore contracts in the history of Senvion.

The wind farm, consisting of a total of 152 Senvion MM92 and 23 Senvion MM82 type turbines CCV, is expected to produce enough electricity to supply about 106 000 households with clean energy. Towers, blades and converters are sourced locally from Quebec.

At the occasion, Andreas Nauen, CEO of Senvion SE, commented: “With the completion of Rivière-du-Moulin, Senvion has an impressive footprint in Quebec which will continue to grow.”

Despite the considerable size of the project and the number of turbines, grid connection has been right on schedule. Up to 585 people in total have been working to achieve that goal, including about 20 Senvion commissioners from Canada, the US and Germany at peak times.

Helmut Herold, CEO North America at Senvion Canada Inc., said: “I am very proud to see phase one of Rivière-du-Moulin reaching commercial operation. Thanks to the great team effort of all partners and our dedicated and very experienced Senvion team, installation and commissioning of the wind farm went smoothly and we finished perfectly on schedule.”

 

About Senvion Canada:

Senvion Canada Inc. currently counts about 250 employees in Canada and has offices in Toronto, Montreal and Vancouver. It is the hub of the North American business. The company started its Canadian operations out of Montreal in the province of Quebec where it is supplying more than 1.2 GW by 2016. The Welland blade production facility is operated by PowerBlades, a wholly owned subsidiary of Senvion SE. More at www.senvion.com.ca
 

Source:
Senvion
Email:
info@senvion.com
Link:
www.senvion.com/...



All news from Senvion GmbH

No_logo

news in archive





Keyword Search

© smart dolphin Gmbh 1999 - 2024 | Legal Notice | Windfair Editors | Privacy Policy | The Windfair Pocket Wind 2020